How was a prefabricated steel school with 2,160 places built in four months?

The Third High-Tech Prefabricated School is northeast of the intersection of Shennan Avenue and Huanggang Road in Futian District, Shenzhen. It occupies approximately 12,000 m², with a floor area of 12,319 m², 48 classes and 2,160 school places. It was among the first projects under Futian's Double Ten programme of ten permanent and ten prefabricated schools.

The school uses a full steel frame, steel-bar truss decking and ALC interior and exterior walls. It achieved a 76% prefabrication rate, structural topping out in 30 days and full handover in four months. The original presentation sets out five core concepts and six technical advantages.

Conventional construction faces energy use, pollution, low productivity and labour constraints. Standardized design, factory fabrication, assembly-based construction, digital management and intelligent operation provide a path towards greener, more sustainable building methods.

Special thanks: China Construction Seventh Engineering Division; China Academy of Building Research; Shenzhen Futian District Education Bureau; and Shenzhen Jiuzhou Construction Technology. Source: GSIN Green Building Division.

How was a prefabricated steel school with 2,160 places built in four months? — original report image 1How was a prefabricated steel school with 2,160 places built in four months? — original report image 2How was a prefabricated steel school with 2,160 places built in four months? — original report image 3How was a prefabricated steel school with 2,160 places built in four months? — original report image 4How was a prefabricated steel school with 2,160 places built in four months? — original report image 5How was a prefabricated steel school with 2,160 places built in four months? — original report image 6How was a prefabricated steel school with 2,160 places built in four months? — original report image 7How was a prefabricated steel school with 2,160 places built in four months? — original report image 8How was a prefabricated steel school with 2,160 places built in four months? — original report image 9How was a prefabricated steel school with 2,160 places built in four months? — original report image 10How was a prefabricated steel school with 2,160 places built in four months? — original report image 11How was a prefabricated steel school with 2,160 places built in four months? — original report image 12How was a prefabricated steel school with 2,160 places built in four months? — original report image 13How was a prefabricated steel school with 2,160 places built in four months? — original report image 14How was a prefabricated steel school with 2,160 places built in four months? — original report image 15How was a prefabricated steel school with 2,160 places built in four months? — original report image 16How was a prefabricated steel school with 2,160 places built in four months? — original report image 17How was a prefabricated steel school with 2,160 places built in four months? — original report image 18How was a prefabricated steel school with 2,160 places built in four months? — original report image 19How was a prefabricated steel school with 2,160 places built in four months? — original report image 20